Baurecht
Latest

Construction crane as an aviation obstacle: permit before erection

When a construction crane qualifies as an aviation obstacle under Austrian law and which permit should be checked before erection.

BRANDAUER Rechtsanwälte
Your law firm

BRANDAUER Rechtsanwälte

Salzburg law firm for real estate, construction and corporate law

Every matter is handled by a coordinated team of lawyers, legal staff and specialists. In construction cases we look at contract, evidence, deadlines and commercial consequences together.

18 September 2026 · Mag. Bernhard Brandauer, Rechtsanwalt

A construction crane may qualify as an aviation obstacle under the Austrian Aviation Act. This is a separate aviation-law issue. It does not replace building-law review or the question whether the crane swings over neighbouring land.

Before erection, the owner and crane company should therefore check whether the site lies in a safety zone or whether the statutory height criteria outside a safety zone are met. Depending on the result, an exemption permit may be required.

The relevant facts are the location, height, terrain, proximity to an aerodrome and the purpose of the installation. A later permit should not be treated as a reliable cure for work that has already started.

Classify your situation

What should be clarified before erection?

Answer two short questions. You receive initial guidance on the site, documents and the next sensible step.

Already know you want to get in touch? Go straight to the enquiry form.

01 Question 1

How far has the project progressed?

The timing shows whether planning or an immediate response is the main issue.

All paths at a glance

Overview of all answers.

01

The aviation-law classification should be clear before ordering and erecting the crane.

Record the location, maximum height, jib configuration and intended operating period. Then check whether a safety zone or the height criteria in section 85 Aviation Act are relevant.

Do not begin erection until the required permits and any conditions have been clarified.

02

Complete information makes it possible to assess whether an exemption permit and conditions are required.

Compare the technical data with section 85 Aviation Act. For an aviation obstacle outside a safety zone, section 91 generally requires a permit from the competent authority.

The aviation permit remains separate from permits required under other laws.

03

Missing technical information can conceal the permit issue.

First secure the exact location, the highest possible crane height, terrain and aerodrome references and the intended purpose. Section 92 requires information on the location, type, characteristics and purpose of the aviation obstacle.

Until this is clarified, the planned erection should not be treated as permitted.

When a construction crane is an aviation obstacle

Section 85 Aviation Act lists, within safety zones, structures, cranes, antennas and comparable installations among aviation obstacles. The relevant question is whether the object penetrates the surfaces defined by the safety-zone regulation.

Outside safety zones, section 85(2)(1) covers objects at least 100 metres above the ground. A further situation concerns objects exceeding 30 metres on a natural or artificial elevation that rises more than 100 metres above the surrounding landscape.

Height therefore cannot be taken from the mast height alone. Terrain, reference level and the precise site must be assessed together.

Check the safety zone and site first

Whether a site lies in a safety zone is separate from whether the crane may swing over neighbouring land. Aviation law protects air traffic and concerns the location and height of the obstacle.

The initial file should therefore contain a scaled site plan, crane position, highest jib position, terrain level and any aerodrome reference. An approximate distance or oral estimate is not enough for a reliable decision.

A building-law or trade-law permit does not automatically answer the aviation-law question. The procedures and responsibilities remain separate.

When an exemption permit is required

Under section 91 Aviation Act, an aviation obstacle outside a safety zone may generally be erected, altered or extended only with a permit from the authority competent under section 93. The provision expressly refers to an exemption permit.

The Aviation Act permit does not replace permits required under other laws. This remains true even if the crane is used only temporarily for a construction project.

A later increase in height, a change of position or a material change in the jib configuration should trigger a renewed review. The change may affect the aviation-law classification.

What the application must state

Section 92(1) requires information on the location, type and characteristics and purpose of the aviation obstacle. For a construction crane, the application should match the technical documents.

A useful file includes the site plan, maximum height, reach, operating period, intended mode of operation and any proposed marking. The competent authority may request additional documents or evidence.

Under section 92(2), the exemption permit is to be granted if aviation safety is not impaired. It may be conditional, time-limited or subject to requirements, especially regarding marking.

Permit validity and project timing

Section 92(3) contains a specific timing rule. If erection, alteration or extension does not begin within two years after the exemption permit becomes final, the permit expires.

If operation does not start within one year after erection, or remains suspended for more than two years, the authority may revoke the permit for aviation-safety reasons and order removal at the owner’s cost. The operator must notify the authority of non-commencement or suspension.

These periods must be distinguished from the short planned duration of a construction crane. They concern the effectiveness of the exemption permit and do not replace an early review before work starts.

Review points

Aviation-law review of the crane

These points separate aviation-law classification from other construction-site issues.

Document location, height and permit separately
Review area Specific question Legal reference
Location Is the crane in a safety zone or a relevant nearby area? Section 85 Aviation Act and safety-zone rules
Height What maximum height does the crane reach above ground and in relation to terrain? Section 85(2) Aviation Act
Permit Has erection, alteration or extension been approved under aviation law? Section 91 Aviation Act
Application Are location, type, characteristics and purpose stated completely? Section 92 Aviation Act

This overview does not replace an authority decision or advice on the individual case.

Important: An aviation permit is separate from a building-law crane permit and from an agreement concerning neighbouring land. Check the current wording of section 85 Aviation Act, section 91 and section 92. Arrange an initial consultation (EUR 72)

FAQ

Construction crane as an aviation obstacle

Is every construction crane automatically an aviation obstacle? +

No. Safety zones, height, terrain and the requirements of section 85 Aviation Act are relevant. The specific site and technical data must be assessed.

Is a building-law permit for the crane enough? +

A building-law permit does not automatically answer the aviation-law question. Under section 91, the required permits may exist alongside one another.

May the crane be erected before the exemption permit? +

If the crane qualifies as a permit-required aviation obstacle, the exemption permit should be obtained before erection. The planned start date should therefore be coordinated with the permit status.

What information is important for the application? +

Section 92(1) names the location, type and characteristics and purpose of the aviation obstacle. For a construction crane, these facts should be supported by a site plan and technical height data.

Topics
Construction craneAviation obstacleAviation ActExemption permitConstruction site

Defects, a remuneration dispute, looming litigation?

In construction law, deadlines and evidence decide. Call us directly or send an email, callback within one business day.

Contact

A direct line to the firm.

Address

BRANDAUER Rechtsanwälte GmbH Giselakai 51 5020 Salzburg