Contractor dies during construction: works contract, personal performance and partial remuneration

Contractor dies during construction: when section 1171 ABGB ends the works contract and what heirs may claim for usable material and work performed.

BRANDAUER Rechtsanwälte
Your law firm

BRANDAUER Rechtsanwälte

Salzburg law firm for real estate, construction and corporate law

Every matter is handled by a coordinated team of lawyers, legal staff and specialists. In construction cases we look at contract, evidence, deadlines and commercial consequences together.

13 September 2026 · Mag. Bernhard Brandauer, Rechtsanwalt

When a construction contractor dies during a private building project, the client must separate two questions: did the work depend on the contractor's special personal qualities, and what value do the material and work on the site have?

Section 1171 ABGB ends a works contract only for work where those special personal qualities matter. The death of an individual therefore does not automatically end every construction contract. A contract with a company and the death of its managing director require a separate assessment.

If the contract expires, section 1171 ABGB allows the heirs to claim the price of prepared usable material and a part of the remuneration appropriate to the value of the work performed. A reliable record of the work status and usability is essential.

Assess your situation

What applies after the contractor's death?

Answer two questions about the contracting party and personal performance. You will receive an initial indication of the documents to prepare next.

Already know you want to get in touch? Go straight to the enquiry form.

01 Question 1

Who did you appoint to carry out the construction work?

For the first classification, it matters whether an individual contractor was the contracting party or whether the contract was made with a company.

All paths at a glance

Overview of all answers.

01

If special personal qualities were decisive, the works contract expires on the contractor's death.

Section 1171 ABGB links expiry to work for which the contractor's special personal qualities matter. Secure the agreement, scope of works and all arrangements concerning personal performance. These documents show whether the work can continue in its original form.

In this situation, the heirs may claim the price of prepared usable material and a part of the remuneration appropriate to the value of the work performed. The account should therefore identify usable material and the value of the work separately.

02

The death of an individual contractor does not by itself end a construction contract.

Section 1171 ABGB requires special personal qualities as the reason for expiry. If that connection is absent or remains unclear, do not treat the contract as ended without reviewing the documents. Read the scope, representation arrangements and previous performance together.

Record in writing with the heirs or the responsible contact person which works remain outstanding and which solution is sought for the site. Continuation requires a separate review of the contract and the actual construction process.

03

The death of a managing director is a different case from the death of an individually appointed contractor.

If a GmbH or another company was the contracting party, that company remains the starting point for the client relationship. The death of one manager therefore does not answer whether the works contract continues. The contract, organisation of the work and legal position of the person who acted must be checked.

Separate who is the contracting party, who performed the work and who may make statements about continuation. A personal performance duty under section 1171 ABGB must not be transferred to a company case without review.

04

Where the contracting party is unclear, the documents determine the next classification.

Collect the order, offer, order confirmation, invoices and correspondence. Check whether the deceased person appears as contracting party, sole trader or only as a contact person.

Also record the status of each trade and the material on site. Only then can you assess whether section 1171 ABGB applies and which accounting or continuation step is useful.

Who was the client's contracting party?

Start by identifying the contractor. The contract, offer and invoices may name an individual sole trader. They may also name a GmbH or another company while a particular person performs or supervises work on site.

This distinction shapes the entire case. Section 1171 ABGB refers to work where the contractor's special personal qualities matter. The specific work must be examined. A personal relationship, professional title or presence on site does not by itself prove that personal performance was owed.

The death of a managing director is a different trigger where a company is the contracting party. The company remains the contractual counterpart to be examined. Representation, outstanding work and project organisation follow from the contract documents and the way the project was run.

When special personal qualities are decisive

A personal connection is more likely where the client selected the contractor for individual expertise, design or performance. Standardised or division-of-labour construction work may lead to another result. The agreed work and its content determine the classification.

Review the contract for wording on personal performance, employees, transferability and the organisation of the work. The scope of works, offer and pre-construction communications may also show which qualities were decisive for the appointment.

The death alone does not establish automatic termination. The presence of material on the site does not establish continuation either. The personal connection to the promised work must be clarified first.

Expiry or continuation of the works contract

Section 1171 ABGB provides for expiry when the contractor's special personal qualities were material to the work. In that situation, the original order cannot simply be treated as continuing unchanged.

If that personal quality was not decisive or cannot be established from the documents, death does not end the construction contract merely as an event. The contracting party, organisation of the work, outstanding duties and communication with the estate or company must then be addressed separately.

The provision also expressly deals with the death of the client. If the client dies, the heirs remain bound by the contract. That statement concerns the client side and must be kept separate from the conditions applying to the contractor side.

Which partial performance can be remunerated?

If the works contract expires because of the contractor's death, section 1171 ABGB names two bases for the heirs' claim. It covers the price of prepared usable material. It also covers a part of the remuneration appropriate to the value of the work performed.

The account must therefore identify which material was prepared and is usable for the project. Ordered goods that were never prepared, unusable parts and unsupported cost assertions cannot simply be treated as the same item. The condition and usability of the material belong in the site record.

The work must also be assessed by value. A general invoice for the entire agreed remuneration does not show which part was performed and became economically useful to the client. Measurement records, photographs, plans, delivery notes and payment records provide a traceable basis.

Legal classification

Which situation applies?

The decisive question is the contracting party and the importance of personal qualities.

Contractor death and possible legal consequences
Contractor status Question to check Effect on the account
Individual, personal performance Were special personal qualities material to the work? Section 1171 ABGB may cause the works contract to expire.
Individual, personal link unclear What do the contract, scope and project history show? Death and continuation require a document-based assessment.
Company as contracting party What was the deceased person's role in the company? Managing director death and company contract continuation are separate issues.
Expiry established Which material is usable and what work was performed by value? The heirs may claim these two components under section 1171 ABGB.

The table does not replace a review of the contract and actual site condition.

Process

Organise the site and account in four steps

A separate record of the project prevents disputes about contract continuation, material and partial remuneration.

  1. undefined

    Secure the contracting party

  2. undefined

    Review personal performance

  3. undefined

    Record the site status

  4. undefined

    Coordinate the account

Subscribe to legal updates: Receive new articles and legal information from the firm through BRANDaktuelle Rechtsnews. Subscribe to the newsletter. If you would like to discuss the contract, site status and account, you can arrange an initial consultation.

Documents that support the next decision

The review needs the signed contract with all schedules, the offer, scope of works and amendments. Add invoices, payment records, delivery notes, site diaries, plans and messages to the file.

Record the site status at the relevant time with photographs, measurements and a list of outstanding work. For material, note whether it was prepared, delivered, installed and usable for the specific project.

Only then can you discuss continuation, handover and accounting with the estate or company. A clear chronology keeps the contractor's death separate from issues arising solely from insolvency, termination or defects.

FAQ

Contractor dies during construction: common questions

Does every construction contract end when the contractor dies? +

No. Section 1171 ABGB provides for expiry only where the contractor's special personal qualities matter to the work. The contract, scope and organisation of performance must be reviewed.

What if the contractor operated through a GmbH? +

The death of the managing director is different from the death of an individually appointed works contractor. The company remains the initial contractual counterpart. Its representation, outstanding work and continuation must be assessed separately.

What may the heirs claim if section 1171 ABGB applies? +

Section 1171 ABGB refers to the price of prepared usable material and a part of the remuneration appropriate to the value of work performed. The entire agreed remuneration does not follow automatically.

How can usable partial performance be proved? +

Useful evidence includes dated measurements, photographs, plans, delivery notes, payment records and a list of usable materials. The work and material should be shown separately in the account.

Is this the same as the construction company becoming insolvent? +

No. The death of an individual and company insolvency are different triggers. An insolvency, termination or defects review may be needed as well, but it does not replace the section 1171 ABGB analysis.

Topics
ContractorDeathWorks contractPartial performanceRemunerationABGB

Defects, a remuneration dispute, looming litigation?

In construction law, deadlines and evidence decide. Call us directly or send an email, callback within one business day.

Contact

A direct line to the firm.

Address

BRANDAUER Rechtsanwälte GmbH Giselakai 51 5020 Salzburg