Existing and additional use
Separate the existing well use from the additional construction-water extraction. Record volume, operating times, pump and the expected effect on the water level.
Planning construction water from a private well? Review extraction, discharge, infiltration, documents and the authority process under water law.
BRANDAUER Rechtsanwälte
Salzburg law firm for real estate, construction and corporate law
Every matter is handled by a coordinated team of lawyers, legal staff and specialists. In construction cases we look at contract, evidence, deadlines and commercial consequences together.
Construction water from a private well should only be used once the extraction, purpose and water route have been clarified. The fact that a well is privately owned does not by itself make temporary construction use unproblematic under water law.
The classification depends on the source, volume, period, technical installation and treatment of the used water. Discharge into a sewer or watercourse raises a separate set of questions.
This article addresses water-law questions concerning temporary extraction and discharge during construction. Drinking-water quality, the original construction of a well, the building permit for the structure and civil-law neighbour claims require separate assessment.
Construction water from a private well will generally come from groundwater. The first legal question is therefore whether the landowner uses the water for the necessary household or business demand, or whether the construction site creates an additional and separate use.
Section 10 of the Austrian Water Rights Act 1959 contains an exemption from approval in defined circumstances for groundwater use by the landowner. The exemption is connected, among other things, with necessary household or business demand, the type of extraction and a reasonable relationship between the extraction and the land owned.
Temporary use for concrete, cleaning or other construction work must therefore be described by reference to the actual project. Calling the installation a private well does not replace the assessment of extraction volume or the later water route.
Under section 10(2) of the Austrian Water Rights Act 1959, approval by the water authority is required in other cases where groundwater is developed or used, the groundwater regime is affected, or an installation for that purpose is built or changed. Artesian wells require approval under section 10(3).
A construction project must therefore make the extraction volume, pump capacity, operating period and effect on the well and groundwater traceable. An existing approval must also be checked to see whether it covers the intended use and technical arrangement.
The water-law assessment is separate from the question whether the well already exists lawfully. A change to the pump or pipework may be relevant in the same way as a materially more intensive use during construction.
Use of the water and its later discharge are separate review points. Section 32 of the Austrian Water Rights Act 1959 covers impacts on waters that may directly or indirectly affect their condition. It expressly includes, among other things, putting substances into waters and measures through which substances enter the soil and pollute groundwater.
For discharge into a sewer or watercourse, record volume, condition, solids, turbidity and discharge point. The sewer operator may impose additional technical or contractual conditions. Its consent does not replace any required water-law assessment.
Infiltration on the property depends on the soil, water level, absorption capacity and possible effects on third-party rights. The route must be designed to avoid wetting, erosion and simply moving the problem to another location.
The competent water authority depends on the location and the particular project. For Salzburg, the Province describes the approval procedure and the project components required under section 103 of the Austrian Water Rights Act 1959. Before filing, a project for which approval is sought must be notified to the water-management planning body.
A project suitable for review states its purpose, type, scope and duration. For a water-use installation, the application should include the requested quantity and the expected effects on waters together with protective measures. For an insertion into waters, it should describe quantity, type, condition and protective measures.
For construction planning, bring the site plan, parcel number, well and pump data, pipe route, extraction quantity, operating periods, water quality, treatment, discharge point and responsibilities together in one consistent project file.
Section 10(4) of the Austrian Water Rights Act 1959 provides for an authority measure on application in certain cases where lawful groundwater uses are substantially affected. In practice, construction-water extraction should therefore be planned and monitored so that effects on other uses become visible early.
Useful records include the well’s starting condition, measurements during extraction, pump times and water levels. If an impact is alleged, its cause, period and concrete effect must be kept distinct and supported by technical evidence.
A neighbour’s procedural position depends on the particular water-law procedure and possible impact. Without the file and technical facts, it is not possible to give a reliable general answer that a neighbour can stop the project or has no legal avenue.
Start with a technical description of the complete route: well, extraction, use, collection, treatment and discharge. This makes it possible to assess whether existing rights are sufficient or whether approval, amendment or an additional consent is needed.
Next, involve the water authority, technical planner and, where relevant, the sewer operator using the same plan version. The Province of Salzburg describes the review, expert assessment and decision in an approval procedure based on the documents required by section 103 of the Austrian Water Rights Act 1959.
Once extraction, route, measurements and competence are clear, the construction contract should allocate responsibility for pump operation, maintenance, records and notifications. This keeps the water-law solution aligned with the construction sequence.
Practical tip: Keep a separate construction-water log with pump times, volumes, water levels, discharge route and unusual events. Further legal updates are available through Brandauer Legal News.
That depends on the existing use, extraction volume, pumping equipment and relationship to the land owned. Section 10 of the Austrian Water Rights Act 1959 must be assessed against the project and the existing well.
Yes. Discharge must be reviewed separately from extraction. Depending on the route, volume and condition of the water, water-law requirements and additional sewer-operator conditions may apply.
Useful documents include the approval or water-register extract, site plan, well and pump data, extraction volume, operating period, water route, discharge point, water-quality information and a measurement and maintenance concept.
In construction law, deadlines and evidence decide. Call us directly or send an email, callback within one business day.
Address
BRANDAUER Rechtsanwälte GmbH Giselakai 51 5020 Salzburg
Phone
+43 662 6280000